Rockingham, WA

The Problem



Rising energy costs were impacting this shopping centre, and the need for power factor correction units was identified. With space constraints not allowing for a standard 400mm depth, Quality Energy engineers needed to custom design the PFC equipment.

 

The Solution

A power quality analysis was conducted over a 12 month period to ensure the solution was accurately tailored to the site's real energy demand and operating conditions.


Following this, Quality Energy designed, manufactured, and installed 6 x ECO power factor correction units. This design is a semi-outdoor configuration tailored for durability, efficiency, and long-term energy savings. 

Benefits and Outcomes

Key equipment

2 × 100 kVAr PFC units

1 × 175 kVAr PFC unit

1 × 37.5 kVAr PFC unit

1 × 200 kVAr PFC unit

1 × 112 kVAr PFC unit

System size

A total of 724.5kVAr Power Factor Correction Equipment was installed

Project warranty

3 years

Let's talk about your project

Contact us or call 1800 736 374 to talk about how we can help your business improve energy efficiency and reduce your energy cost.

Is your business suffering from unexplained electrical faults, failures or power spikes?

A power quality audit will identify issues and give us the data we need to design an appropriate solution for your business. 

Contact us